File:
agents/sdlc/04-planning.md · Model: Opus · Tools: Bash, Read, WritePurpose
The planning agent turns approved requirements into an executable project plan: a work breakdown structure (WBS) with owners and durations, milestones that deliver testable value, a dependency map between tasks, and a risk register with real mitigations. Its own framing: a plan with vague tasks is a plan that will be misunderstood, re-estimated, and missed.Core principle
Every task has an owner role, a duration in days, and a one-sentence definition of done that does not use the word “implement.” Every top risk has a mitigation — not “monitor the situation,” but a specific action with a trigger.The stage prompt frames the stakes directly: the architecture agent (stage 06) sizes a system for this plan, and the Jira agent (stage 05) creates tickets straight from this WBS — a badly structured plan produces tickets nobody can execute and a risk register nobody reads.
What it does
- Reads
requirement_spec.json(stage 02’s output) - Builds the WBS — breaks requirements into 1–5 day tasks, each with one owner and one deliverable, grouped into milestones (phases that deliver testable value), with dependencies mapped between tasks
- Builds the risk register — each risk scored H/M/L on probability and impact, with a mitigation and a trigger; flags the top 3 risks that could block delivery
- Writes
plan.json
Inputs and where it sits in the pipeline
Planning is stage 4 of 15, sitting directly between Requirements (stage 02 — via stage 03 documentation) and Jira (stage 05), and it feeds forward into Architecture (stage 06):- Reads:
requirement_spec.jsonfrom stage 02 - Consumed by: stage 05 (Jira tickets generated from the WBS) and stage 06 (system sized against this plan)
Output
Per the canonical stage registry (src/core/harness/stages.js), stage 04-planning produces the artifact plan.json:
Brownfield behavior
rstack-agents adopt deliberately skips this stage entirely — plans belong to new work, not to a system that already exists. On an adopted run that later triggers a real planning pass (a new change against an existing baseline), the agent is instructed to plan only the new change, sized against the adopted baseline, reading the harvested 00-environment and 06-architecture artifacts (each marked source: "brownfield-adoption") as ground truth rather than re-scaffolding anything that already ships. Risks in that mode should include brownfield-specific ones: untested legacy paths, implicit API contracts, and the study-before-modify cost.
Quality self-check and completion
Before reporting done, the agent verifies every task has an owner role, a duration, and a one-sentence definition of done; that dependencies are mapped; and that every top-3 risk has a specific mitigation (not “monitor”). It also asks itself, as an operational self-improvement step, whether any estimates felt unreliable due to ambiguous scope, or whether a risk was found with no clear mitigation — logging genuine discoveries viarstack memory append.
Completion status follows the standard Task Contract vocabulary:
Escalation rule: after 3 failed attempts to build a coherent WBS, or if resource/timeline constraints make the plan obviously undeliverable, the agent stops and escalates rather than producing a plan it doesn’t believe in.